Project
Description:Krech Ojard was responsible for the reconstruction of 1200 feet of the General Mills loading dock in Superior, WI. Features in part of this project included the grain loading dock, wood cribbing & wood piling and sheet pile retaining wall with a timber deck. This project was funded by the Wisconsin Department of Transportation and the Wisconsin Harbor Assistance Program. Engineering completed within budget and time constraints.
Pictured directly above is a pipe pile grouping for a new mooring dolphin ready to be formed for its new concrete cap.
|
Special
Issues and Needs:
Reconstruction of loading dock, wood cribbing, wood piling & sheet pile retaining wall with a timber deck.
Services
provided:
• DNR and ACOE Permitting
• Geotechnical Investigation
• General arrangement and demolition plans
• Turning cell and Mooring dolphin design
• Timber modification/design/repair
• Catwalk and catwalk bent design
• Prepare technical specifications
• Demolition/Construction
• Construction Management
• Final inspection and project
close-out
Project Summary:
The project was completed in 2006 on schedule, to budget, and
to the client's satisfaction.
|