| US
Steel Minntac Mountain Iron,MN |
 |
Project
Description:Krech Ojard & Associates,
P.A. installed a new limestone unloading facility to handle
4,000 tons of limestone an hour, delivered by bottom-dump and
side-dump railcars. The facility includes a dust collection
system and a back-up hydraulic car dumper.
|
Special
Issues and Needs:

Services
provided:
• Developed original design concept.
• Provided complete design services, from concept to start-up.
Project
Summary:
This project was completed in November of 1995. The design developed
by Krech Ojard & Associates, P.A. saved the client more than $1
million from their original cost estimates.
|