US HIGHWAY 2 RECONDITIONING
This US Highway 2 WisDOT roadway improvement project involved milling and overlaying from CTH D to Clevedon Road (9.3 Miles). Krech Ojard & Associates provided construction management of the reconstruction for intersection improvements at CTH P and CTH F. The improvements included widening to allow for dedicated right and left turn lanes, new curb and gutter, and new storm sewer.
Other minor intersections were improved with new curb and gutter and larger radii. All work was done in stages with temporary widening or flagging to allow US Highway 2 to remain open to traffic.
Krech Ojard offers a highly capable multi-disciplined team that provides the professional services needed to deliver successful transportation facility improvements. KOA provides multidisciplinary planning, engineering and program and construction management services for all types of transportation projects.